M12 Motorway NSW

Client: CPB Georgiou JV Location: NSW

Jurovich Surveying undertook surveying works on a 6.1-kilometre west section of the M12 Motorway NSW, between The Northern Road, Luddenham and Badgerys Creek.

  • Constructed as part of a joint venture between CPB and Georgiou.
  • Includes the airport (new Western Sydney) interchange and Elizabeth Drive fly over.
  • A shared user path providing an active transport link.
  • New bridges over Luddenham Road, Cosgroves Creek and Badgerys Creek.

Jurovich Surveying have been involved since the early works program. We conducted the POSI survey as per Surveyor-General’s Direction No.11 (SGD.11).

Our involvement in the project progressed to the construction phase. Survey activities including setout and as-constructed relating to bridge construction, culvert, drainage, earthworks, road subgrade, sub base and pavement.

Jurovich Surveying are also providing support for Cadastral survey requirements, boundary marking and WAE surveys where required.

Key Information

Client

CPB Georgiou JV

Location

NSW

Duration

2024
Back to projectsBack to projects